Columbia Class Submarine:
Delivery Hinges on Timely and Quality Materials from an Atrophied Supplier Base
GAO-21-257: Published: Jan 14, 2021. Publicly Released: Jan 14, 2021.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-4841
oakleys@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
Over the next 20 years, the Navy plans to build Columbia class ballistic missile submarines while also constructing the attack submarine fleet—a pace unmatched since the Cold War.
In previous building booms, there were more suppliers available to the nation's nuclear shipbuilders than there are today. The Columbia class program's success is contingent on timely delivery of quality materials, but quality problems with some materials caused delays during early construction.
We recommended that the Navy provide Congress with supplier readiness information and reassess when to conduct inspections at supplier facilities to limit quality problems.
Rendering of the Columbia Class Submarine
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-4841
oakleys@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
The Navy's schedule for constructing the first submarine of the new Columbia class is threatened by continuing challenges with the computer-aided software tool that Electric Boat, the lead shipbuilder, is using to design the submarine. These challenges will likely impede construction because the shipbuilder is late in completing design products used for building the submarine. To ensure construction begins on schedule, the Navy modified its design contract with Electric Boat to include an option for constructing the first two submarines and requested sufficient authority from Congress for fiscal year 2021 to exercise it. Navy officials stated, however, that the Navy's budget request is lower than its current cost estimate, and it is not informed by an independent cost assessment. As a result, the program will likely need more funding to reflect the increased estimate.
Quality problems with supplier materials caused delays during early construction. These quality problems included missile tubes (depicted below) with defective welds. As the shipbuilders expand outsourcing to suppliers, quality assurance oversight at supplier facilities will be critical for avoiding further delays.
Quad Pack of Four Submarine Missile Tubes
However, the Navy has not comprehensively reassessed when to seek additional inspections at supplier facilities that could better position it to identify quality problems early enough to limit delays.
Why GAO Did This Study
The Navy plans to invest about $128 billion in 12 Columbia class nuclear-powered ballistic missile submarines. The shipbuilders will construct the Columbia class at the same time as the Virginia class attack submarines. They plan to rely on materials produced by a supplier base that is roughly 70 percent smaller than in previous shipbuilding booms.
Congress included a provision in statute for GAO to examine the program's status. This report assesses the Navy's efforts to complete the design for the lead Columbia class submarine and actions the shipbuilders and the Navy have taken to prepare for construction and ensure the lead submarine is delivered according to schedule and quality expectations.
GAO assessed Navy and shipbuilder design progress against cost and schedule estimates, reviewed documents, and interviewed officials about supplier readiness and quality assurance. This is a public version of a sensitive report that GAO issued in November 2020. Information that the Department of Defense (DOD) deemed sensitive has been omitted.
What GAO Recommends
GAO recommends that the Navy (1) provide Congress with updated cost information, (2) include information on supplier readiness in its annual report to Congress, and (3) reassess when to seek additional inspections at supplier facilities. DOD concurred with the recommendations but disagreed with some of the report's details. GAO incorporated DOD's comments as appropriate and maintains the validity of the findings, as discussed in the report.
For more information, contact Shelby S. Oakley at (202) 512-4841 or oakleys@gao.gov.
Recommendations for Executive Action
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: The Secretary of the Navy should provide Congress with information from the milestone decision authority meeting that convened in August 2020. This should include updated cost and schedule information following the milestone decision authority's review of the independent cost assessment and assessment of the program's ability to reduce development risks. (Recommendation 1)
Agency Affected: Department of Defense: Department of the Navy
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: The Secretary of the Navy should ensure that the Navy includes an update on the status of critical supplier readiness as part of the annual report it provides under the provisions of the 2018 National Defense Authorization Act to further inform Congress on the status of the Columbia class program's performance goals during design and construction. (Recommendation 2)
Agency Affected: Department of Defense: Department of the Navy
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: The Secretary of the Navy should ensure that the Supervisor of Shipbuilding, Conversion and Repair (SUPSHIP), in collaboration with Columbia class program management, assesses whether additional materials require government source inspections as soon as practicable and if the Navy believes further government source inspections are required, take action to ensure the shipbuilder includes the inspection clauses in contracts with suppliers. (Recommendation 3)
Agency Affected: Department of Defense: Department of the Navy
Explore the full database of GAO's Open Recommendations
»
Feb 26, 2021
-
Defense Transportation:
DOD Can Better Leverage Existing Contested Mobility Studies and Improve TrainingGAO-21-125: Published: Feb 26, 2021. Publicly Released: Feb 26, 2021.
Feb 25, 2021
-
Military Service Uniforms:
DOD Could Better Identify and Address Out-of-Pocket Cost InequitiesGAO-21-120: Published: Feb 25, 2021. Publicly Released: Feb 25, 2021.
Feb 24, 2021
-
Defense Budget:
Opportunities Exist to Improve DOD's Management of Defense SpendingGAO-21-415T: Published: Feb 24, 2021. Publicly Released: Feb 24, 2021.
Feb 22, 2021
-
Service Acquisitions:
DOD's Report to Congress Identifies Steps Taken to Improve Management, But Does Not Address Some Key Planning IssuesGAO-21-267R: Published: Feb 22, 2021. Publicly Released: Feb 22, 2021.
Jan 21, 2021
-
Close Air Support:
Actions Needed to Enhance Friendly Force Tracking Capabilities and Fully Evaluate TrainingGAO-21-99: Published: Jan 21, 2021. Publicly Released: Jan 21, 2021.
Jan 19, 2021
-
GPS Modernization:
DOD Continuing to Develop New Jam-Resistant Capability, But Widespread Use Remains Years AwayGAO-21-145: Published: Jan 19, 2021. Publicly Released: Jan 19, 2021.
Jan 14, 2021
-
Department of Defense:
Actions Needed to Improve Accounting of Intradepartmental TransactionsGAO-21-84: Published: Jan 14, 2021. Publicly Released: Jan 14, 2021.
Jan 12, 2021
-
DOD Critical Technologies:
Plans for Communicating, Assessing, and Overseeing Protection Efforts Should Be CompletedGAO-21-158: Published: Jan 12, 2021. Publicly Released: Jan 12, 2021.
Dec 10, 2020
-
Climate Resilience:
DOD Coordinates with Communities, but Needs to Assess the Performance of Related Grant ProgramsGAO-21-46: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020. -
Electromagnetic Spectrum Operations:
DOD Needs to Address Governance and Oversight Issues to Help Ensure SuperiorityGAO-21-64: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020.
Looking for more? Browse all our products here